The sequence
| Step | Who does it | What happens |
|---|---|---|
| 1. Survey | Your surveyor | Corners pinned, lines run, setbacks and easements known. |
| 2. Vegetation clearing | RRE | Brush, small trees and unwanted trees removed from the footprint, drive corridor and work zone. Keep-list trees marked and left. See site development & land preparation. |
| 3. Stumps | RRE | Stumps and root mass grubbed out where the pad and drive will go, so the grader is not fighting roots. See stump grubbing. |
| 4. Grading and pad | Grading or excavation contractor | Soil moved, pad built, drainage shaped. Not RRE. |
| 5. Utilities | Utility contractors | Water, power, septic and data installed. RRE can clear vegetation along the route; it does not install anything. |
| 6. Build | Your builder | Foundation onward. |
The order matters. Clearing before the survey risks cutting on the wrong side of a line. Grading before the stumps are out leaves roots in the pad.
Keeping shade trees near the footprint
A mature live oak or longleaf beside a house is worth the conversation, and it has to happen before the machines arrive. Every property has something worth keeping. On a homesite, the question is which trees can survive the build, not only which ones you like.
Three things decide it.
- Distance from the footprint. A builder needs room to work, and a tree inside that zone usually goes.
- The root zone. Trucks and stored material compact roots well beyond the trunk, so a kept tree needs its ground protected through construction.
- The tree itself. A leaning or hollow pine over a bedroom is a hazard.
We agree the keep list with you at the site visit, flag it on the ground and clear around it. Bring your builder to the site visit.
Permits and buffers
Ordinary vegetation clearing on private rural land in Georgia and South Carolina generally does not need a state permit. Counties and towns are a different matter. Beaufort County, the Town of Bluffton and the Town of Hilton Head Island, among others, regulate removal of protected or specimen trees, and the rules change. Check the current rule with your county before clearing. [FPO: cite exact page + access date — SRC-017] [FPO: RRE's policy on confirming local tree ordinances before a homesite clear — VAL-041]
Wetlands and water buffers are regulated separately, by the U.S. Army Corps of Engineers and the state environmental agency, and sometimes the county. If the lot has a creek, a marsh edge or ground that stays wet, read clearing near water and confirm the buffer before you fix the footprint. For the whole picture, see do you need a permit to clear land?. None of this is legal advice; ask your surveyor and the county.
Timing with your builder
Clear once the site plan and footprint are fixed, and not long before the grader is due. Clear too early and the lot regrows before the builder arrives. Clear too late and the schedule stalls on you.
Wet ground is the other factor. Low Lowcountry lots and Midlands hardwood bottoms hold water after rain, and hurricane season runs June through November. Tell us the builder's start date and we will plan the clearing to land just ahead of it. Timing is confirmed at the site visit and written into the project quote; a 25% deposit is required to schedule.
Start your homesite right
Send hello@rreforestry.com the town or county, the lot size, a site plan or sketch, photos of the lot and the way in, and your builder's start date. Estimates are free and follow a site visit. Request a consultation.
Frequently asked questions
Can you clear just the footprint and the driveway?
Yes. Many owners clear the house site, the drive and a working zone, and leave the rest as woods. The agreed boundary is flagged on the ground and written into the scope before the work starts.
Do you grade the pad or build the driveway?
No. RRE prepares the land: vegetation and stumps. The pad, drainage and driveway are built by a grading or excavation contractor after we are done.
I have not closed on the lot yet. Can I clear it?
Only with the owner's written permission. Talk to your agent or counsel before scheduling work on land you do not own.